What has recently gone wrong for land buyers, diaspora investors and home builders in Nigeria, what people are worried about online, and how we would approach each one.

Last updated 2 November 2026. This page is a dated, sourced digest of public news and online posts, not a live feed. We check and add cases regularly. Cases are described as reported; many are allegations that have not been proved in court. We leave out the names of private individuals and companies, and Landiz had no involvement in any of them. Nothing here is legal advice.
10sourced cases below
₦450mlargest single case listed here
1,639+building-collapse deaths since 1971 (BCPG)
Land & title

Plot “allocations” that never came: about 30 buyers, an estimated ₦450 million

What was reported. Police in Lagos reported an arrest after about 30 people said they paid roughly ₦9.45 million each over two years for plots through a company. The allocations were never delivered, and the office was reportedly abandoned. The suspect is cooperating with detectives and has not been convicted.

The worry behind it. “Is this seller or company real, and will I actually get the plot I am paying for?”

How we would approach it
  • Check the company at CAC and confirm who actually owns the land before any payment (Steps 1–3).
  • Pay against verified milestones and into a company account, never to an individual or in cash.
  • Ask for a registered Deed of Assignment and survey plan up front, not “after payment”.

Source: Peoples Gazette / NAN

Land & title

₦125 million paid for Oregun land that was allegedly under a court dispute

What was reported. The EFCC returned ₦125 million to a Lagos buyer. According to the report, the land was already the subject of a legal dispute and court orders that the seller allegedly did not disclose before taking payment. The buyer got his money back through a petition; many do not.

The worry behind it. “Could there be a court case on this land that nobody told me about?”

How we would approach it
  • Court registry litigation search for suits, judgments and injunctions (Step 4).
  • Lands Registry search for recorded owners and encumbrances (Step 2).
  • Written confirmation from the seller that there is no pending dispute, kept on file.

Source: The Mirror (Nigeria)

Land & title

15 acres in Epe sold on paper: ₦21 million, then an arraignment

What was reported. The EFCC arraigned a man over an alleged ₦21 million fraud, saying a company paid him for 15 acres at Ilara, Epe that he represented he could sell. The defendant is facing trial and the allegations are yet to be proved in court.

The worry behind it. “The seller showed me land and papers. How do I know he can actually sell it?”

How we would approach it
  • Independent site visit with a surveyor to confirm boundaries, access and who is occupying (Step 6).
  • Community verification with the traditional authority and neighbours (Step 5).
  • Family tree analysis to confirm the seller has the authority to sell (Step 7).

Source: Peoples Gazette

Land & title

Registry check showed the plots “were not for sale”

What was reported. At a trial that opened in January 2026, a complainant said that verification at the Alausa Land Registry showed the properties he had paid for were not for sale. The payments in the case, for plots at Ogombo and Ibeju-Lekki, were allegedly made between 2015 and 2019, so the problem stayed hidden for years. It is an allegation at trial, not a finding.

The worry behind it. “I paid years ago and I am only now finding out the land was never available.”

How we would approach it
  • Search the registry before the first payment, not after years of waiting (Step 2).
  • Confirm the survey plan with the Surveyor-General’s office (Step 3).
  • Do not hand over cars, cash or “part payments” on promises alone.

Source: The Mirror (Nigeria)

Land & title

Lekki land sold on a forged deed, a state prosecution

What was reported. Lagos State filed an amended four-count charge over the alleged fraudulent sale of a 1.08-hectare parcel in Lekki, including conspiracy, forgery and property fraud. The charge covers a deed said to have been executed between two companies. The defendants are yet to be convicted.

The worry behind it. “The documents look genuine. Could they still be forged?”

How we would approach it
  • Document forensics on the C of O, deed and survey plan (Step 1).
  • Registry search to match the document to the official record (Step 2).
  • Independent Nigerian lawyer’s opinion on title, under a separate engagement.

Source: The Nigeria Lawyer

Land & title

A family says impersonation and forgery are behind land sales on the coast

What was reported. A Lagos family asked the governor and the police to step in over a land dispute, alleging impersonation, forgery and fraudulent collection of money linked to land in the fast-growing coastal area. These are the family’s allegations.

The worry behind it. “Is the person selling to me really the family’s authorised representative?”

How we would approach it
  • Family tree analysis and written family consent (Step 7).
  • Community verification with the family head and the community’s traditional leadership (Step 5).
  • Never pay “omo onile” or agents in cash without a receipt and a signed document.

Source: allAfrica / Vanguard

Diaspora

Diaspora buyers wait years for apartments they paid for

What was reported. Nigerians in the US, Europe and the Middle East told ThisDay they paid for Lekki apartments from 2020 and 2021 under an agreement to deliver within 12 months. They said they were repeatedly asked for extra payments, took the matter to regulators and the EFCC, and had still not received their homes. The developer said the project had been hit by inflation and that work was continuing, and did not deny the delay.

The worry behind it. “I paid, and now I am abroad and cannot tell whether anything is really being built.”

How we would approach it
  • Verify the developer’s land title and approvals before the first payment (Steps 1–3).
  • Independent site visits with dated, photo-evidenced progress reports, so “work is ongoing” can be checked.
  • Release money against verified progress. Landiz has no authority to release funds and holds none.

Source: ThisDay

Building & supervision

Ikorodu collapse: owner abroad was funding the build, three people died

What was reported. LASEMA said early findings pointed to substandard materials in a two-storey building that collapsed in Ikorodu, killing three people. Residents alleged that 10 mm rods were used instead of 16 mm. The owner was reported to be abroad and sending money home to fund construction. The cause is still under investigation.

The worry behind it. “I am paying from abroad. How do I know the contractor is using the specified steel, blocks and cement?”

How we would approach it
  • Inspect before concrete is poured: reinforcement size, spacing, cover and formwork.
  • Check materials against the agreed specification and bill of quantities.
  • A pass, watch or fail report for every stage, sent only to you.

Source: The Frontier

Building & supervision

Lagos collapse kills at least nine; 27 rescued with injuries

What was reported. Al Jazeera reported that a building collapse in Lagos on 25 June 2026 killed at least nine people, with 27 rescued injured. It noted that rapid urbanisation, substandard materials and weak enforcement have long put residents at risk.

The worry behind it. “Is my building structurally safe, and who is checking while it goes up?”

How we would approach it
  • Independent stage inspections from setting-out to roof (nine stages).
  • Confirm approved drawings, permits and a registered engineer are in place.
  • Do not occupy or pay the final instalment until snagging and structural checks pass.

Source: Al Jazeera

Building & supervision

Builders’ institute: collapses linked to missing professional supervision

What was reported. The Nigerian Institute of Building said investigations into most collapses point to poor construction management, inferior materials, the absence of professional supervision and unqualified people on site. Separately, the Building Collapse Prevention Guild counts about 679 incidents and at least 1,639 deaths between 1971 and 2025.

The worry behind it. “How common is this, and what actually reduces the risk?”

How we would approach it
  • Put qualified, independent eyes on site at the stages that cannot be re-inspected once covered.
  • Keep dated photo and measurement records you can show your lawyer or contractor.
  • Use a checker who is paid by you, not by the contractor or supplier.

Source: Peoples Gazette; The Guardian (Nigeria)

From online platforms

What people are worried about

Threads, posts and articles where buyers and builders describe the fears behind these cases, and what tends to help.

Reddit · diaspora thread, Jul 2026

“What is the one thing that makes you terrified to build a house back home?” Diaspora members and relatives who have managed builds trade stories about trust, money and distance.

The worry. Trust and distance: paying people you cannot see.

What helps. Independent stage reports, so you see the site yourself without flying home.

Read the original ↗

Cofellow Nigeria · guide for Nigerians abroad

Many Nigerians abroad know someone whose house has been “90% done” for years, or whose contractor keeps asking for extra funds. The article advises splitting payments into stages and having a Nigerian solicitor review contracts.

The worry. Endless “top-up” requests and stalled roofs.

What helps. Pay per verified stage; agree the stages and evidence in writing before you start.

Read the original ↗

Viral X post, covered by Yen.com.gh

A man in the US said that after six years of sending money to relatives for a house, he found no house had been built and the money was gone.

The worry. Family or friends managing your money, with no records.

What helps. A neutral third party who reports to you only and has no stake in the project.

Read the original ↗

BusinessDay · diaspora investor report

A UK-based investor financing a Lekki duplex reportedly returned to find a demolition notice because the project had no valid survey and no building permit. A SURCON-sealed survey and a fast-tracked approval reportedly saved it.

The worry. Building first, approvals later.

What helps. Check the survey, permit and approvals before the foundation, not after the roof.

Read the original ↗

Vanguard · Abuja market report, Apr 2026

Buyers losing money in Abuja are “not careless people”, the developer quoted said; they include professionals, civil servants and diaspora Nigerians. A 2025 industry analysis cited puts annual real-estate fraud losses near US$4 billion.

The worry. Believing that only careless people get caught.

What helps. A repeatable checklist applied to every purchase, whoever the seller is.

Read the original ↗

Facing something similar?

Tell us the location and what you were given. We reply with a scope and a written quote, and we tell you honestly if you do not need us.

If you believe you have been defrauded, also report to the police or the EFCC and keep every receipt, message and document.